To Update Component Versions (Design Center)

You can update an existing project to use a different version of a dependency without losing your dependency configurations.

Connectors and other components that are versioned independently from the Mule runtime are considered dependencies.

Here are the steps to update a project that has at least one dependency, such as a connector:

  1. Click the Dependency icon manage dependency versions design center d96c7 on the left side bar.

    A list of all dependencies and their versions is used in your project is shown.

  2. Hovering over a dependency, click the Options icon manage dependency versions design center 018a5 and choose Change Version > version number.

  3. Verify that updated component’s configuration have not changed. The only time your configuration will change will be if the version changes also implies changes to the fields.